Lab
Assembly Timeframe
|
| |
| 8/4 - Assemble Racks / Layout |
|
| 8/6 - Set Racks and Run Ladder Raceway |
|
| |
|
| 8/9 - Pull in cable / Route cable |
|
| 8/10 - Pick-up and install equipment |
|
| |
|
| 8/12 - Install and bundle cables |
|
| 8/16 - Install remaining waterfalls and side wire |
|
| 8/18 - Install equipment racks to tabletops |
|
| |
|
| 8/24 - Organize equipment power cords on racks |
|
| |
|
| |
|