Building the Lab
After six months of planning, the Cisco Systems lab was assembled during summer quarter 1999.
20-124 CAD image

 

Lab Assembly Timeframe
 
8/4 - Assemble Racks / Layout

8/6 - Set Racks and Run Ladder Raceway
 
8/9 - Pull in cable / Route cable
8/10 - Pick-up and install equipment
 
8/12 - Install and bundle cables
8/16 - Install remaining waterfalls and side wire
8/18 - Install equipment racks to tabletops
 
8/24 - Organize equipment power cords on racks
 
 

 