"Timeless
Software Solutions" |
|
|
|
|
|
|
Software
Release Criteria |
|
|
Quartzware
has established the following formal criteria that must
be met before the software can be released.
- At
least 90% of planned code is complete.
We had planned on completing
approximately 2579 lines of code.
We actually completed 2478 lines of code.
2478/2579 96%
- The
slope of the code growth curve for the
week prior to release must be less than
50%.
We produced 55 lines of code in week 8,
and 89 lines of code in week 9.
55/89 = 62%
- At
least 90% of binary miniature milestones
are complete.
We finished about all of our miniature
milestones and completed all of the
modules we had assigned for this release
with the exception of Find. Find was
taken out of the staged delivery plan a
week ago.
- There
are no severity 1 open defects.
All
defects that have been reported to this
date have been fixed.
- The
number of defects reported must be at
least 80% of predicted.
We
had planned on finding 80 defects and
actually found 90.
90/80 = 113%
- 75%
of all severity 2 reported defects must
have been fixed.
All defects that have been reported to
this date have been fixed.
- The
Release Sign-Off form has been signed by
all parties.
- In the week prior to release, the ratio
of defects reported to defects fixed must
be less than 25%
15/27 = 56%
02/01/01
Created, John Pham 3/13/01 Updated for release 3, Tony
Tomarchio
|