Progress for Stage 3
LOC Complete Stage 1 and 2 Week 7 Week 8 Week 9 Total
Actual 5989 89 687 160 6925
Actual To Date 5989 6078 6765 6925 6925
Actual Percent 87% 88% 98% 100% 100%
Planned 5989 145 471 299 6904
Planned To Date 5989 6134 6605 6904 6904
Planned Percent 87% 89% 96% 100% 100%
Defects Found Stage 1 and 2 Week 7 Week 8 Week 9 Total
Actual 102 0 0 3 105
To Date Actual 102 102 102 105 105
Actual Percent 100% 100% 100% 103% 103%
Planned 85 3 8 6 102
Planned To Date 85 88 96 102 102
Planned Percent 83% 86% 94% 100% 100%
Resources used Stage 2 Week 7 Week 8 Week 9 Total
Kevin 38.75 11 12 26 87.75
Kamil 49.25 7 5.25 15.5 77
Antony 62.25 12 14 22 110.25
Josh 94.25 4.5 4.25 19 122
Sean 55 11.5 8.5 23 98
Total 299.5 46 44 105.5 495
Planned 360 60 60 60 540
Percent of Planned Estimate 55% 64% 72% 92% 92%
Total To Date Actual 299.5 345.5 389.5 495 495
Planned To Date 360 420 480 540 540
Planned to date Percent 67% 78% 89% 100% 100%
Progress for Stage 2
LOC Complete Stage 1 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Total
Actual 2438 309 1762 1342 138        
Actual To Date 2438 2747 4509 5851 5989        
Actual Percent 44% 50% 82% 107% 109%        
Planned 1861 331 1579 1162 141 260 156 0 5490
Planned To Date 1861 2192 3771 4933 5074 5334 5490 5490 5490
Planned Percent 34% 40% 69% 90% 92% 97% 100% 100% 100%
Defects Found Stage 1 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Total
Actual 47 0 8 19 28        
To Date Actual 47 47 55 74 102        
Actual Percent 48% 48% 57% 76% 105%        
Planned 50 8 13 11 3 6 4 2 97
Planned To Date 50 58 71 82 85 91 95 97 97
Planned Percent 52% 60% 73% 85% 88% 94% 98% 100% 100%
Resources used Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
Kevin 2 5 6.5 7.75 8.5 9      
Kamil 3 12.25 9 10 7 8      
Antony 4 3 7 5.75 22 20.5      
Josh 6.5 10 9 15 36 17.75      
Sean 4.5 7 4.5 10 15.5 13.5      
Total 20 37.25 36 48.5 89 68.75      
Planned 60 60 60 60 60 60 60 60 60
Percent of Planned Estimate 33% 62% 60% 81% 148% 115%      
Total To Date Actual 20 57.25 93.25 141.75 230.75 299.5      
Planned to Date 60 120 180 240 300 360 420 480 540
Planned to date Percent 11% 22% 33% 44% 56% 67% 78% 89% 100%