Top 10 Risks List

 


 

Risk

Likelihood
(1-10)

Impact
(1-10)

Retirement
(1-10)

Risk Resolution Progress

1

CVS Problem

9

8

4

Train developers in using CVS as well as make them aware of previous problems and solutions

2

Misunderstanding of requirements

9

8

8

More customer interaction throughout course of the project

3

Not accounting for or not knowing about certain risks

6

10

8

More customer interaction throughout course of the project

4

Lack of Required Knowledge or Skills

6

8

7

Revise and execute training plan

5

Lack of Customer Interaction

7

9

7

Keep contact with customer on a weekly basis

6

Lack of Team Communication

5

6

3

Keep Action items list and all other pertinent documents for team members up to date and detailed. Try to limit the need for “How do I….” type of communication

7

Last minute Web Site Updates

9

5

4

Teach all team members how to update the team web page

8

Members Lack of Knowledge on Change Control

6

5

3

Make sure all members read procedure and follow

9

Computer System Failure

2

8

7

Use the labs in the college

10

Team Member Incarcerartion

10

2

2

Give member a laptop and keep him working. If all else fails plan team severance package.

 


Date

Author

Change

3/4

A. George

Updated Version

2/25

A. George

Updated Version

2/17

K. Baranowski

Updated Version

2/04

K. Baranowski

Updated Version

1/31

K. Baranowski

Updated Version

1/29

K. Blomseth

Initial Posting