3-07-2002

Team Accomplishments
 In lab today we integrated some of our new features and saw them in action – it was great!  We are now more focused on our Stage 3 objectives.  We were supposed to have ALL the code done today but we are a little behind.  We will have to pick up the pace a little in order for a successful and punctual release.

Unfinished Tasks:
All modules done being coded

Schedule Revisions:
Finish code ASAP

Group Problems:
none

 

3-05-2002

Team Accomplishments
Today the instructor expressed his concerns for the progress of our project.  He told our class that he wanted us to stop whatever development we have going and sacrifice whatever features were necessary in order to allow for proper testing and completion.  Our group decided not to implement the change robot color, organize levels, and the tutorial features.  We will finish the other features planned for Stage3 (multiplayer chat, high scores list, sound, and level editor). 

Unfinished Tasks:
none

Schedule Revisions:
New objectives for Stage 3 release

Group Problems:
none

 

2-28-2002

Team Accomplishments
We did not have much lab time tonight because of a long presentation that the instructor gave.  In the remaining half hour of lab time our team distributed current action items for next time and small design changes. 

Unfinished Tasks:
New Top 10 Risks List and LOC counting procedure

Schedule Revisions:
none

Group Problems:
Sean is unfamiliar with GUI elements.

 

 

2-26-2002

Team Accomplishments
Our team met for lab and discussed our current status since our end-of-Stage2 Recalibration.  We are on schedule.  We also had our first weekly customer meeting.  We showed him our preliminary User Interface Prototype for our level editor and received his input on changes that need to be made.  Also the customer showed us an example of what he would like the sound to be.

Unfinished Tasks:
none

Schedule Revisions:
Add 4 buttons for the robot starting point and direction faced

Group Problems:
none

 

 

2-25-2002

Team Accomplishments
During our last lab meeting, our team exchanged team responsibilities.  Kevin is now the Designer/Integrator, Kamil is the QA and web administrator person, Antony is the Configuration Manager, Josh is the Test Team Manager, and I (Sean) am the Team Manager.  Then we handed out new jobs for next class time and scheduled weekly meetings with the Customer to ensure that every week our project will be on track.

Unfinished Tasks:
none

Schedule Revisions:
none

Group Problems:
none

 

2-11-2002

Team Accomplishments
We had a meeting with the customer to review requirements for the project on Monday, which proved to be useful. We finished all coding and testing and submitted the program to the customer on Thursday, and checked the rest of the documents on the website for submission to the instructor on the first meeting of this upcoming week. The program was accepted conditionally, provided that we fix some bugs that were present, which has been done.

Unfinished Tasks:
none

Schedule Revisions:
none

Group Problems:
none

 

2-04-2002

Team Accomplishments
We coded most of the required features for the Stage 2 release, and a lot of the test cases were written. The Integration plan was changed to be sorted by date as per instructor request. We updated several documents that needed updating. Sean finished his Test Matrix.

Unfinished Tasks:
none

Schedule Revisions:
Updated to include submission dates to customer and instructor.

Group Problems:
none

 

1-28-2002

Team Accomplishments
Implementation was begun this week, with Kevin, Josh, and Kamil following the Integration plan to decide what modules were to be written. The team has been working to become accustomed to using cvs, with errors such as locking it up when trying to upload updated coad.

Unfinished Tasks:
none

Schedule Revisions:
none

Group Problems:
none

 

1-21-2002

Team Accomplishments:

Josh Finished the Design Revisions and the Integration Plan was created. The SPMP and SQAP were updated for the quarter. The CVS repository was set up on Kamil’s Latte Account. Project Visibility was begun. The Change Control plan and Training plan were put up on the website.

Unfinished Tasks:
none

Schedule Revisions:
Updated for 206

Group Problems:
none

 

1-14-2002

Team Accomplishments:
Lucky Strike Software received a new member, Sean Pinto, and lost Janice Lin.

Kevin Blomseth - Project Manager
Sean Pinto - Testing
Josh Thompson - Designer and Integration Manager
Kamil Baranowski - Configuration Management, Analyst, Risk Officer, Webmaster
Antony George - Quality Assurance

We updated the website with the updated team information and the Staged Delivery Plan. Josh has begun design revisions

Unfinished Tasks:
none

Schedule Revisions:
none

Group Problems:
none