Stage 2 Milestones

Dates

Completed?

Requirements update

1/17/2002

Yes

Staged Delivery Plan written

1/17/2002

Yes

Project Plan Updated

1/17/2002

Yes

Build Instructions written

1/22/2002

Yes

Quality Assurance Plan Updated

1/17/2002

Yes

Process Definitions written (Refer to web page template)

Instructor defined, see his schedule

Yes

Detailed Design updated

1/22/2002

Yes

Test Cases written

1/31/2002

Yes

Source Code written and updated for Stage 2

1/31/2002

Yes

Source Code integrated completely for Stage 2

2/2/2002

Yes

Program submitted for Acceptance Testing

2/7/2002

Yes

Program submitted to Instructor

2/12/2002

Yes

Designer/Instructor Meeting

2/13/2002

Yes

 

 

 

Stage 3 Milestones

 

 

Requirements Update

2/19/2002

Yes

Project Plan Updated

2/20/2002

Yes

Quality Assurance Plan Updated

2/21/2002

Yes

Recalibration for Stage 3

2/24/2002

Yes

Coding for Stage 3

2/26/2002 - 3/5/2002

Yes

Customer Meeting

2/26/2002

Yes

Writing Test Cases for Stage 3

2/26/2002 – 3/7/2002

Yes

Customer Meeting

2/28/2002

Yes

Customer Meeting

3/5/2002

No

Source Code integrated completely for Stage 3

3/7/2002

Yes

System Testing for Stage 3

3/7/2002 – 3/12/2002

Yes

User Manual written (SRS)

3/11/2002

Yes

All tracking/process documents updated

3/11/2002

Yes

All Defects Removed

3/11/2002

Yes

Program submitted for Final Acceptance

3/12/2002

Yes

 


Date

Author

Change

3/10

S. Pinto

Updated for Stage 3 with updated dates

2/25

S. Pinto

Updated for Stage 3 with initial estimates

2/11

K. Blomseth

Corrected errors

2/04

K. Blomseth

Updated Schedule

1/18

K. Blomseth

Initial Posting