Schedule
 

 

Note: This schedule is subject to change at any time.

Date Task
Th 1/11 Deliverables Critique
Tu 1/16 First Drafts of: Project Plan, Detailed Schedule, Lines of code (Est./Actual), Change Control Plan, Quality Assurance Plan

LOC Estimates complete

Th 1/18 Stage 1 Release Date
Tu 1/23 Project Planning Documents on team web page (except Recalibration and Project History) - This is ongoing
Th 1/25 Requirements Traceability complete
Visibility information updated and on web
PSP Procedure
Time Accounting Procedure
Unit Developer Procedure
Build Procedure / Build Report
Integration Plan for Release 2 complete
Assign modules and begin coding
Tu 1/30 Formal Change Control complete
Risks List on web
Defect Tracking in place and started
Coding (refer to Integration Plan for more information)
Th 2/1 Coding (refer to Integration Plan for more information)
Tu 2/6 Testing
Integration and Release
Th 2/8 Testing
Integration and Release
Customer Acceptance Test
Tu 2/13 Stage 2 Release Date
Th 2/15 Midterm Examination
Tu 2/20 Recovery period from Release 2 (i.e. make changes and update anything needed after Release 2)
Th 2/22 Update tracking information after Release 2
Sun 2/25

Split Panes researched; implemented if feasible

Coding and integration into project complete for
Getting a Field
Setting the Value for a Field
Tu 2/27

Dalbey's coding assignment completed
User manual updated to reflect approved change proposals

Coding and integration into project complete for
Invoking a Method
Change Proposal 4
Change Proposal 12-14 (12 is dependent on 13 and 14)
Th 3/1 Black-box homework assignment completed
Coding and integration into project complete for
Removing a Returned Data Item
Moving a Returned Item to Parameters
Inspect a Returned Data Item
Fri 3/2
Coding and integration into project complete for
Change Proposal 1
Change Proposal 2
Change Proposal 6
Change Proposal 16 (if proposal is approved Thursday)
 
Coding for following features ready for review
Inspect Parameter Objects
Inspect Returned Objects
Change Back Ground of Logging TabbedPane
Sat 3/3

Preparation / review of code for software inspection complete (who's reviewing what)

Software inspection of code for following features complete
Inspect Parameter Objects
Inspect Returned Objects
Change Back Ground of Logging TabbedPane
Unit Testing for following modules complete
ETAMainModel.classToName
ETAMainView.NewParameterObjectAction.actionPerformed
ETAMainView.addMethodRow
InstantiateClassDialog constructor
InstantiateClassDialog.onOK
MethodRow constructor
Following features integrated into build
Inspect Parameter Objects
Inspect Returned Objects
Change Back Ground of Logging TabbedPane
Sun 3/4
testing / defect removal
Mon 3/5 testing / defect removal
Tu 3/6

White-box homework assignment completed

testing / defect removal

Wed 3/7 testing / defect removal
Th 3/8
testing / defect removal
Fri 3/9

System test cases written for
3.1, 3.3, 3.6, 3.7
2.1, 2.5, 2.6

Sat 3/10

System test cases written for
3.2, 3.4, 3.5
2.2, 2.3, 2.4

User Manual updated
Staged Delivery Plan updated

Sun 3/11

testing / defect removal (no open severity-1 defects, 75% severity-2 fixed)
online help for ETA complete
UI Prototype Updated

Customer Acceptance Test

Mon 3/12 All tasks in Release Checklist completed
Tu 3/13

Stage 3 Release Date

Th 3/15 Final Project Submission
Th 3/22
0110-0400pm
Final Exam Sec 02


Detailed Schedule maintained by Michael Hebron - Project Manager

Last modified 03/08/01