Action Items
 

 

Completed Action Items are shaded
Late Action Items are colored Red
Action Items that are still being worked on are not colored
Action items shared by whole team are colored yellow

Name Action Items Date Assigned Date Due
Completed
ALL Read Chapter 18 for team meeting on Thursday 3/13 3/15  
Phil Create CD for final submission 3/13 3/15  
MikeH Email Phil directory structure / contents that will be on final CD 3/13 3/14  
Jon Finish writing system test scripts 3/13 3/14  
MikeP Create ReadMe file for final CD 3/13 3/14  
Wes Create one more build (to accomodate change in ETAViewAbstract constructor made in lab) 3/13 3/14  
Phil Add Keyboard Shortcuts section to user manual 3/8 3/10 3/10
Phil Implement cheap blinky workaround 3/8 3/10 3/10
MikeH Revise release criteria #7 3/8 3/8 3/8
MikeH Update UI Prototype 3/8 3/11 3/12
Jon Javadoc comments for MyRobot (cancelled) 3/8 3/12  
Jon Update unit test procedure (add details about documenting tests) 3/8 3/9 3/9
Apel Javadoc comments for Assert (cancelled) 3/8 3/12  
Apel Figure out how to spawn a browser to display help file 3/8 3/11 3/13
Wes Update Staged Delivery Plan 3/8 3/10 3/10
ALL Write System Test Cases (see test matrix for who's assigned what) 3/8 3/10 3/10
Phil Research blinking defect 3/6 3/7 3/7
Phil Disable object pool buttons when not necessary (cancelled) 3/6 3/8 (cancelled)
MikeH Route output to status pane to log files (to assist testing) 3/6 3/7 3/7
Jon Research how long it takes to write / perform a system test case, assign system test cases to rest of group 3/6 3/10 3/8
Jon Update system test case and test matrix 3/6 3/10 3/8
MikeP Revise software inspection summaries (list defects found) 3/6 3/9 3/9
MikeP Add accelerators to menu items (to assist testing) 3/6 3/7 3/7
Wes Modify PrimitiveValueFactory so that iterator returned is sorted alphabetically (to assist testing) 3/6 3/7 3/8
Wes update integration plan (add requirement #s for Stage 3 features) 3/6 3/6 3/6
Apel Fix returnedData.isPrimitive defect 3/6 3/6 3/6
Apel add debug flag to assert class, reroute message to ETA.err stream 3/6 3/6 3/6
Phil Perform unit testing on assigned modules 3/1 3/3 3/5
MikeH Perform unit testing on assigned modules (pushed back) 3/1 3/8  
Jon Perform unit testing on assigned modules (pushed back) 3/1 3/8 3/8
MikeP Perform unit testing on assigned modules (pushed back) 3/1 3/8  
Wes Perform unit testing on assigned modules (pushed back) 3/1 3/8  
Apel Perform unit testing on assigned modules (pushed back) 3/1 3/8  
Apel Write assertion class (follow dr. dobbs example from dalbey's resource page) 3/1 3/3 3/3
Mike P Create Software Inspection Procedure document 2/27 3/1 3/1
Jon Update Unit Testing Procedure 3/1 3/3 3/3
ALL Black Box Testing Homework 2/27 3/1 3/1
ALL Inspecting / Testing "party" in lab 2/27 3/3 3/3
ALL Prepare for software inspections (reviewers) 2/27 3/3 3/3
ALL Code assigned methods due Thursday 2/27 3/1 3/1
ALL Code assigned methods due Friday(that are to be inspected Saturday) 2/27 3/2 3/2
Phil Implement assigned change proposals (2) 2/27 3/2 3/2
Mike H Use JMetric to find methods with cyclomatic complexity > 5 to unit test 2/27 2/27 2/27
Mike H Implement assigned change proposal (16 - coding) 2/27 3/2 3/7
Jon Update Unit Testing Procedure 2/27 3/1 3/1
Mike P Implement assigned change proposals (6 - coding; 12-14) 2/27 3/2 3/2
Wes Implement assigned change proposal (1) 2/27 3/2 3/2
Apel Update Change Proposals page with who's been assigned to implement which resolutions 2/27 3/1 3/1
Apel Update Change Proposals Page with results from last meeting 2/22 2/24 2/24
Mike H Continue Mike P's research on having split panes for the application 2/22 2/25 2/25
Phil Update User Manual to reflect changes that were approved in last change control meeting (rescheduled to be due Friday after code for change proposals is integrated) 2/22 3/2 3/2
Phil Update User Manual with more details about requirements 2/20 2/22 2/22
Phil Update Staged Delivery Plan 2/20 2/22 2/22
Phil Complete New Staff Document Review 2/20 2/22 2/22
Phil Code assigned modules 2/20 2/27 2/27
Wes Update Requirements Traceability Matrix (finer level of detail needed) 2/20 2/22 2/22
Wes Go through change proposals and update integration plan 2/20 2/27 2/28
Wes Contact customer about outstanding change proposals 4, 6, and 11 2/20 2/22 2/22
Wes Code assigned modules 2/20 2/27 2/27
Wes Complete New Staff Document Review 2/20 2/22 2/22
Mike H Release 2 Recalibration 2/20 2/22 2/26
Mike H Revise Detailed Schedule 2/20 2/22 2/26
Mike H Code assigned modules 2/20 2/27 2/27
Mike H Complete New Staff Document Review 2/20 2/22 2/22
Mike P Prepare explanation of code inspection, advise on when it should be done 2/20 2/22 2/27
Mike P Complete New Staff Document Review 2/20 2/22 2/22
Mike P Code assigned modules 2/20 2/27 2727
Jon Update PSP submission procedure 2/20 2/22 2/22
Jon Complete programming assignment 2/20 2/27 2/27
Jon Complete New Staff Document Review 2/20 2/22 2/22
Apel Complete programming assignment 2/20 2/27 2/27
Apel Complete New Staff Document Review 2/20 2/22 2/22
Apel Code assigned modules 2/20 2/27 2/27
Phil Update Visibility info with Mike H, update other managerial pages on web 2/15 2/20 2/20
Wes Begin assigning methods for Integration plan stage 3 2/15 2/22 2/20
Mike H Update name tags 2/15 2/20 2/20
Mike P Become familiar with Quality Assurance 2/15 2/20 2/20
Apel Update web pages to reflect new staff positions, resolution to Change Proposal 12. Remove Software Project Log from home page 2/15 2/22 2/22
Jon Update Risks List 2/15 2/22 2/22
Phil Complete code walkthroughs (aka code standardization): MethodRowInterface, FieldRow, MethodRow, ParameterRow, ETAViewAbstract 2/8 2/10 2/10
Phil Revise line counts so that they are all standardized (ie use FLOCC program) 2/8 2/9 2/9
Phil Update User Manual 2/8 2/13 2/13
Wes Complete code walkthroughs (aka code standardization): ETA, ObjectPool, ObjectInspector, ReturnThread, ThreadFreeList, and OutputAreaStream 2/8 2/10 2/10
Wes Update User Manual 2/8 2/13 2/13
Wes Update Requirements Traceablility Matrix 2/8 2/13 2/13
Wes Conduct system tests 2/8 2/13 2/13
Mike H Complete code walkthroughs (aka code standardization): FieldDataInterface, MethodDataInterface, ParameterDataInterface, ReturnedDataInterface, ParameterDataListener, ReturnedRow 2/8 2/10 2/10
Mike H Update prototype in accordance with some of the logged defects 2/8 2/13 2/13
Mike P Complete code walkthroughs (aka code standardization): ETAMainModel, FieldData, MethodData, ParameterData, ReturnedData 2/8 2/10 2/10
Mike P Update Integration plan 2/8 2/13 2/13
Mike P Update build report 2/8 2/13 2/13
Apel Complete code walkthroughs (aka code standardization): ETAInspectorView, ETAMainView, RowAbstract, ParameterObjectComboBox, ChangeBackgroundDocumentListener 2/8 2/10 2/10
Jonathon Complete code walkthroughs (aka code standardization): InstantiateClassDialog, ConstructorRow, CreatePrimitiveDialog, PrimitiveValueFactory, VisibilityTabbedPane 2/8 2/10 2/10
Phil Code assigned methods for Stage 2 2/6 2/7 2/7
Phil Find and fix defects 2/6 2/13 2/13
Phil Complete Integration plan line counts 2/6 2/8 2/8
Wes Find and fix defects 2/6 2/13 2/13
Wes Ask customer about Change Request 6 2/6 2/8 2/8
Wes Code assigned methods for Stage 2 2/6 2/7 2/7
Wes Write test cases 2/6 2/8 2/13
Mike H Investigate and implement Change Requests 7 and 9 2/6 2/8 2/8
Mike H Code assigned methods for Stage 2 2/6 2/7 2/7
Mike H Find and fix defects 2/6 2/13 2/13
Mike P Investigate impacted methods for Change Request 5 2/6 2/8 2/8
Mike P Find and fix defects 2/6 2/13 2/13
Apel Investigate and implement Change Requests 8 and 9 2/6 2/8 2/8
Apel Find and fix defects 2/6 2/13 2/13
Apel Code assigned methods for Stage 2 2/6 2/7 2/7
Jonathon Find and fix defects 2/6 2/13 2/13
Jonathon Update class diagram 2/6 2/13 2/13
Jonathon Revise and update the pseudocode for Stage 3 2/6 2/13 2/15
Phillip Hansen Update line counts and visibility information 2/1 2/6 2/6
Phillip Hansen Update the detailed schedule 2/1 2/6 2/6
Phillip Hansen Update User Manual screenshots from our current build 2/1 2/6 2/6
Wes Strickland Write smoke test and smoke test report format 2/1 2/6 2/6
Mike Hebron Investigate the tool JMetric and report on its usefullness 2/1 2/4 2/4
Mike Hebron Finish the coding assignments that Jon started 2/1 2/6 2/6
Mike Power Meet with Jon to discuss and update Integration Plan 2/1 2/3 2/3
Apel Yahinian Conduct Internal System testing on the latest build 2/1 2/6 2/8
Apel Yahinian Finalize QA Plan 2/1 2/6 2/8
Jonathon Lee Meet with Mike P. to discuss and update Integration Plan 2/1 2/3 2/3
Jonathon Lee Update Risks List 2/1 2/8 2/8
Jonathon Lee Review design and pseudocode 2/1 2/6
2/6
Phillip Hansen Code assigned methods 1/30 2/1
2/1
Wes Strickland Write Test Plan 1/30 2/6
2/6
Mike Hebron Reorganize menu structure of program 1/30 2/1
2/1
Mike Hebron Update User Manual 1/30 2/1
2/1
Mike Power Code assigned methods 1/30 2/1
2/1
Apel Yahinian Code assigned methods 1/30 2/1
2/1
Jonathon Lee Code assigned methods 1/30 2/1
2/1
Phillip Hansen Complete traing survey and mail to Wes 1/25 1/30
1/30
Phillip Hansen Code assigned methods 1/25 1/30
1/30
Phillip Hansen Revise Time Accounting Procedure 1/25 1/30
1/30
Phillip Hansen Revise Visibility info calculations 1/25 1/30
1/30
Wes Strickland Ask customer to decide about the object inspector 1/25 1/30
2/1
Wes Strickland Post people's responses to training survey 1/25 1/30
1/30
Mike Hebron Code assigned methods 1/25 1/30
1/30
Mike Power Code assigned methods 1/25 1/30
2/1
Mike Power Assign coding to rest of team 1/25 1/25
1/25
Apel Yahinian Code assigned methods 1/25 1/30
1/30
Apel Yahinian Complete training survey and mail to Wes 1/25 1/30
1/30
Apel Yahinian Revise Unit Development Plan 1/25 1/30
1/30
Jonathon Lee Re-run JavaDocs on current build and post on web 1/25 1/30
1/30
Jonathon Lee Code assigned methods 1/25 1/30
2/1
Jonathon Lee Complete training survey and mail to Wes 1/25 1/30
1/30
Phillip Hansen Write Team Accounting Procedure 1/23 1/25
1/25
Phillip Hansen Fill in Visibility information 1/23 1/25
1/25
Phillip Hansen Revise Detailed Schedule 1/23 1/25
1/25
Phillip Hansen Revise Action Items Page 1/23 1/25
1/25
Wes Strickland Update User Manual 1/23 1/24
1/24
Wes Strickland Write Requirements Traceability Matrix 1/23 1/25
2/1
Mike Hebron Update Change Control Plan 1/23 1/25
1/25
Mike Hebron Web Updates (add link to PSP, add JD conding standard link) 1/23 1/25
1/25
Mike Hebron Formulate required knowledge of trainees for our program 1/23 1/25
1/25
Mike Hebron Formal Change Control Plan 1/23 1/30
1/25
Mike Power Write Build Report and Build Procedure 1/23 1/25
2/6
Apel Yahinian Write Unit Developer Procedure 1/23 1/25
1/25
Jonathon Lee Revise Staged Delivery Plan 1/23 1/24
1/24
Jonathon Lee Update Risks List 1/23 1/30
1/30
Phillip Hansen Revise Deliverables part of Project Plan 1/18 Tue 1/23
Tue 1/23
Phillip Hansen Write Stage Delivery Plan and put on web 1/18 Tue 1/23
Tue 1/23
Wes Strickland Setup Teamatic 1/18 Tue 1/23
Tue 1/23
Mike Hebron Web updates 1/18 Tue 1/23
Tue 1/23
Mike Hebron Meeting on Saturday to discuss Staged Delivery and Integration plans 1/18 Sat 1/20
Sat 1/20
Mike Hebron Email Phil notes from Saturday's meeting 1/18 Tue 1/23
Tue 1/23
Mike Power Meeting on Saturday to discuss Staged Delivery and Integration plans 1/18 Sat 1/20
Sat 1/20
Mike Power Start Daily Build process 1/18 Tue 1/23
Tue 1/23
Mike Power Write Integration Plan after Saturday's meeting 1/18 Tue 1/23
1/25
Apel Yahinian Revise Quality Assurance Plan 1/18 Thur 1/25
2/1
Apel Yahinian Create schedule to be put on web 1/18 Tue 1/23
1/25
Jonathon Lee Meeting on Saturday to discuss Staged Delivery and Integration plans 1/18 Sat 1/20
Sat 1/20

 


Action Items page updated and maintained by Mike Hebron - Project Manager

Last updated 03/13/01