Show all your calculations on this page.
Perform the calculations described below and put the current week's
data on the home page.
Keep this page on the team wiki and the version history will be
maintained automatically.
Then beneath your calculations, summarize the data by week in
a table or chart.
LOC | Stage 1 (CPE 308) |
Week 1 | Week 2 | Week 3 | Total | |||||||
Actual | 2000 | 321 | 450 | 250 | ||||||||
Actual To Date |
2000 | 2321 | 2771 | 3021 | ||||||||
Planned | 569 | 473 | 458 | |||||||||
Planned To Date | 2000 | 2569 | 3042 | 3500 | ... | 7000 |
For week 3 you would report 3021 / 7000 vs 3500 / 7000,
i.e.,
43% / 50%
Actual Defects found to
date:
120
LOC Actual To
Date:
3021
Total LOC planned for
project:
7000
Planned defects found to date:
LOC Actual To Date * 50 defect / 1000 lines =
3021 * 50 / 1000 = 151
Planned total defects found:
Total LOC planned for project * 50 defect / 1000
lines = 7000 * 50 / 1000
= 350
Actual defects found %:
(Actual defects found / planned
total)
= 120 /
350
34%
Planned Defects Found to date %:
(Planned defects found to date / planned total ) = 151 /
350
43%
This is reported on home page: 34% / 43%
Defects Found |
Week 1 | Week 2 | Week 3 | ... | Week 9 | Week 10 | Total | ||||
Actual | 10 | 8 | 12 | ... | 23 | ||||||
To Date Actual | 10 | 18 | 30 | ... | 200 | ||||||
To Date Planned | 25 | 50 | 75 | ... | 225 | 250 | 250 |
Defects Fixed | Week 3 | Week 4 | Week 5 | ... | Total | ||||
5 | 8 | 13 | |||||||
A chart showing found versus fixed per week will be needed for
Release
Criteria.
This data does not need to be summarized on Home Page.
System Tests |
Week 3 | Week 4 | Week 5 | ... | Total | ||||
Written | 21 |
23 | 24 | ||||||
Passed | 3 | 12 | 19 |
This data does not need to be summarized on Home Page.
Week 1 | Week 2 | Week 3 | ... | Week 10 | Total | ||||||
Joe | 8.25 | 13.0 | 12.0 | ||||||||
Sue | 12.5 | 11.5 | 10.25 | ||||||||
Bill | 9.75 | 10.0 | 11.5 | ||||||||
Sam | 11.5 | 12.25 | 12.0 | ||||||||
Ted | 10.25 | 9.25 | 10.0 | ||||||||
Total | 52.25 | 56.0 | 55.75 | ||||||||
% of planned | 58% | 62% | 61% |
Week 1 | Week 2 | Week 3 | ... | Total | |||||||
To Date Actual |
52.25 | 108.25 | 164 | ||||||||
To Date Planned |
90 | 180 | 270 | 360 | 450 |
540 |
630 |
720 |
810 |
900 |
900 |
To Date %Planned |
10 |
20 |
30 |
40 |
50 |
60 |
70 |
80 |
90 |
100 |
100 |
For week 3 you would report 164 / 900 vs 270 / 900, i.e.,
18%
/ 30%
Action Items |
Week 1 | Week 2 | Week 3 | ... | |||||||
Completed on time |
40 | 45 | 51 | ||||||||
To Date |
40 |
85 |
136 |
||||||||
Due |
45 | 47 |
53 |
||||||||
To Date |
45 |
92 |
145 |
||||||||
%ontime |
88 |
92 |
93 |